Thursday, November 12, 2026

New Jersey Restricts Data Centers While Warren County Targets Developers

A $1.07 million environmental penalty against a South Jersey data center may seem far removed from northern Warren County. 

But the enforcement action announced Sept. 22 comes as New Jersey puts new rules in place for an industry that communities including Blairstown, Knowlton and Frelinghuysen have already moved to restrict. 

The New Jersey Department of Environmental Protection said inspectors found 62 large natural-gas generators operating without required air pollution permits at the DataOne facility in Vineland. DEP ordered the company to obtain permits or stop operating the generators. 

The case comes as Gov. Mikie Sherrill’s administration rolls out a statewide framework addressing data centers, including electricity costs, resource use and impacts on host communities. 

For Warren County, however, the state action follows months of local debate over a more basic question: Should large data centers be allowed in these communities at all? 

Why Trenton Is Focusing on Data Centers 

Data centers house servers and computing equipment behind cloud storage, artificial intelligence and other digital services. Large facilities can require substantial electricity, while some also use significant amounts of water for cooling. 

Sherrill announced a four-part plan in May focused on electricity costs, energy and water transparency, agreements between developers and host communities, and labor standards. 

A law signed in July creates a separate ratepayer category for large data centers and directs the state Board of Public Utilities to develop rules intended to prevent other electric customers from subsidizing infrastructure needed to serve them. 

Tracking Electricity and Water 

Another law signed Aug. 27 requires data center owners and operators to report energy and water consumption to the BPU twice a year, including water use, water sources and information about on-site and backup power. 

Water is a particular concern in Warren County, Commissioner James Kern III said, because much of the county is within the Highlands region and many residents rely on wells. 

“These facilities use a significant amount of water,” Kern said in an interview with Ridge View Echo. “And most of our county is on well water. So where does that come from? And I think it’s really important that those factors are part of how towns are ultimately zoning.” 

The Delaware River Basin Commission, a federal-interstate agency that manages shared water resources in the Delaware River Basin, is also tracking data center development. 

Elizabeth Koniers Brown, the DRBC’s Director of External Affairs and Communications, told Ridge View Echo that the commission is aware of two proposed data centers across the Delaware River from Warren County, in Lower Mount Bethel and Upper Mount Bethel, Pennsylvania. The Slate Belt Technology Campus in Upper Mount Bethel has two designs proposed: One would occupy about 76 acres; the second, 32 acres. The Lower Mount Bethel Technology Center would take up to 450 acres of land. The average data center is about 100,000 square feet, or about 2.3 acres.

Residents raise concerns about the environmental risks posed by the proposed mega data centers, which would affect communities, residents, wildlife and the integrity of the Delaware River—which would impact NJ communities equally. Noise pollution and quality of life are also among residents’ concerns, as expressed on the No Data Center LMBT’s social media posts.

Neither of the Pennsylvania projects has applied for DRBC approval, Brown went on to say. 

“The DRBC has not yet received any applications for data center projects because the existing data centers in the basin purchase water from public water supply systems rather than operate their own withdrawal systems,” Brown said. 

Brown said the commission is tracking roughly 30 proposed data centers throughout the basin. 

The Vineland case illustrates another issue associated with some facilities: on-site power generation. DEP said each of the 62 natural-gas generators discovered during its July inspection had a capacity of 1,982 kilowatts. NJ state law requires a permit for any generator with a capacity of 37 kilowatts or higher. 

“This enforcement action, by far the largest ever taken against a data center in New Jersey and possibly one of the largest such actions in the nation, sends a clear message that these facilities will not be constructed or operated with impunity in this state,” DEP Commissioner Ed Potosnak said. 

What the Rules Mean for Towns 

The state’s framework also gives municipalities guidance if they decide to consider a data center. 

The Department of Community Affairs has outlined how towns can negotiate Community Benefits Agreements with developers. Such agreements can address infrastructure, emergency services, noise, lighting and pollution while potentially securing investments in roads, schools and workforce development. 

The guidance does not require towns to approve data centers or replace local zoning authority. 

“At the end of the day, I think ultimately in New Jersey, it’s a home rule state, so the towns really have to address it,” Kern told Ridge View Echo. 

Kern said municipalities seeking to restrict data centers need to do so through zoning ordinances rather than resolutions and said a master plan can further clarify where the use fits. 

Warren County Was Already Moving 

Earlier this year, Kern circulated a model ordinance to municipalities considering how to handle large data centers. He compared the issue to warehouse growth several years ago, when towns revisited zoning as development proposals emerged. 

The model ordinance was advisory, leaving each municipality to determine its own land-use rules. 

According to Kern, 18 of Warren County’s 22 municipalities now have protections in place addressing data centers. 

Frelinghuysen adopted an ordinance prohibiting large-scale data centers in June, while Knowlton and Blairstown have also moved to restrict the facilities. Blairstown’s regulations prohibit data centers larger than 5,000 square feet. 

“I would say that it’s important that residents are engaged and aware of what’s going on in their community because ultimately that’s who elected officials work for,” Kern said. 

What’s Next? 

New Jersey’s data center policy is still taking shape. The BPU must develop detailed electricity rules required under the new law, while data centers will face new requirements to disclose energy and water consumption.

For northern Warren County, the issue will continue to play out at multiple levels. Trenton is establishing statewide rules, the DRBC is tracking potential water impacts, and local governments retain an important role in deciding where, and in some cases whether, large facilities fit within their communities. 

Support Local News

Ridge View Echo is a nonprofit newsroom serving Blairstown, Knowlton, Frelinghuysen, Hardwick and Hope. If you value independent local journalism in our community, please support our work.

Related