This should come as music to the ears of anybody who has tried to travel east beyond Warren County for the past five months.

Assemblywoman Aura Dunn, whose district includes Wharton, the town where collapsing mineshafts have been creating sinkholes on the highway since December, received confirmation from the New Jersey Department of Transportation Tuesday morning.

Things are on track for the reopening of those lanes by tomorrow,” Dunn said. “Now, it may be toward the end of the day, but I just had a call this morning with DOT officials, and it is on track.”

The target for reopening the westbound lanes remains the end of next week, the DOT said Tuesday.

And the DOT is aiming for June 26 to fully reopen both directions of I-80.

On Wednesday, two of the three eastbound lanes will be opened initially as work continues along the median. In both cases, two lanes of three will be reopened to traffic initially, including the right lane and the shoulder. The DOT is reminding drivers that the area remains a work zone where fines are doubled, and that the speed limit will be 40 mph.

This will be the same arrangement when two westbound lanes reopen on the westbound side. While the DOT is aiming for the westbound side to be reopened by the Memorial Day weekend, the work could be subject to the weather as it has reached a stage where concrete that can’t be poured during rain is used.

“We’re headed to the Memorial Day weekend, perhaps maybe the most traveled holiday of the year,” said Dunn. “We’ve got to get those people to eat out at those restaurants and get back to serving those local businesses.”

Many businesses have been suffering from congestion and detours caused by the sinkholes since January.

The confirmation of the eastbound lanes is particularly meaningful as several target dates to reopen both sides of I-80 have had to be postponed as additional underground voids caused by the abandoned mines were discovered.

Under the original schedule, I-80 westbound was expected to have two lanes reopened by May 4, according to the DOT. That reopening was been pushed back to the end of May. The delay was due to the sonic drilling process taking longer than expected, said DOT spokesperson Steve Shapiro.

“The abandoned mines and associated shafts are buried features that are not accurately mapped or visible from above,” said Steve Shapiro, a state DOT spokesman. “The extent of these mines was not fully known to the NJDOT prior to the emergence of the sinkholes.”

Meanwhile, Dunn, said in April that she would sponsor legislation that would manage long-term infrastructure risks related to the hundreds of abandoned mines that dot Morris and Warren counties.

“I have requested the drafting of legislation to establish a New Jersey Mine Reclamation Program,” Dunn said. “Modeled in part on successful federal efforts and existing state programs like gas main and lead pipe replacement initiatives.”

Joe Phalon
Contributing Writer

Joe brings decades of journalism experience to the Ridge View Echo, covering everything from local school boards to the U.S. Supreme Court. A former National Law Journal editor and Columbia Law School press officer, he now enjoys telling community stories in Blairstown, where he lives with his wife, Rose, and their two dachshunds.

Support Local News

Ridge View Echo is a nonprofit newsroom serving Blairstown, Knowlton, Frelinghuysen, Hardwick and Hope. If you value independent local journalism in our community, please support our work.

Related